# How to Track Job Extras From Customer Approval to Invoice

Use a phone-friendly extras log and daily handoff to connect approved job extras to their invoice lines.

Published October 29, 2026

A customer asks for more work while your crew is on site. You discuss it, finish the job, and then have to reconstruct that conversation when it is time to invoice.

To track extra work on a construction job, give each requested change its own reference. Keep that reference with the scope, approval, completion record, and one invoice line.

## Check the contract before added work starts

A change order documents changes to scope, cost, and schedule. The construction contract may set the approval process, as [Procore explains](https://www.procore.com/library/how-construction-change-orders-work).

For this job, check who may approve a change and how that approval must be recorded. Save the approval where the crew lead and billing person can find it. A text can be part of the job record, but do not assume a text meets your contract’s requirements.

## Keep one entry for each extra

Use a shared note, spreadsheet, form, or job system that the crew lead can open on a phone. Give each request a unique ID, such as JOB-184-EX-03.

Copy these fields into each entry:

- **Job and extra IDs:** Which job this belongs to, and the unique reference for this change
- **Original scope:** What the agreement already covers
- **Requested change and location:** What the customer wants and where
- **Site record:** A photo, measurement, or short note
- **Proposed price and timing:** The added amount and any schedule effect, including “none”
- **Approver:** Who may authorize the change for this job
- **Approval record:** Required method, approval date, and where the record is saved
- **Status:** The current step
- **Next owner:** Who must act next
- **Invoice line:** The invoice number and line that bills this extra, once issued

Use this status path: requested → priced → awaiting approval → approved → completed → invoiced. Mark a rejected request declined. Keep it in the log so the crew does not mistake it for approved work.

If the scope changes again, record the revision clearly. Give it a new extra ID when it needs a separate approval or invoice line. Do not use one ID for two different billable extras.

## Example: one added outlet

This example is hypothetical; its price is for illustration only.

During a renovation, the customer requests an outlet on the dining-room wall. The field lead creates JOB-184-EX-03, notes that the original scope covers kitchen cabinets and lighting, and saves a photo of the requested outlet location.

The lead records a proposed **$250 extra with no schedule change**, identifies the person authorized under this job’s contract, and sends the defined change through the required approval process. Until that approval is saved, the status stays awaiting approval.

After approval, the crew completes the outlet and the lead marks the entry completed. Billing receives the extra ID, approved scope and price, completion status, and approval-record location. When invoice INV-184 is issued, billing puts the outlet on **line 4**, records INV-184, line 4 in the log, and marks the entry invoiced.

## Hand off extras each day

Before the crew closes out the day:

1. Review extras marked approved or completed.
2. Confirm the approval record is saved with the job.
3. Send billing each completed extra’s ID, scope, approved price, and approval-record location.
4. Have billing confirm receipt and take ownership of the invoice step. Keep approved work that is not yet complete with the field lead.

## Check both sides before invoicing

Compare the log with the draft invoice:

- Every approved **and completed** extra has exactly one matching invoice line.
- Every invoice line for extra work points back to one extra ID and its approval record.
- Each line’s description and amount match the approved change.
- Declined and unfinished work stays off the invoice.

This check makes the record easier to trace. It does not guarantee payment or replace the contract’s change procedure.

For roofing-specific decisions about documenting, pricing, and approving changed work on site, use the [roofing change-order process](https://www.novatori.us/field-notes/roofing-change-order-approval-process). Carry the resulting approved extra through this log and invoice check.